Symbolic Ground-Breaking Ceremony

On 20 January 1999, the ground-breaking ceremony for the entire production complex took place. After that, construction of the fruiting facility began, where the fourth production phase is carried out.

1999

Fertigstellung der Fruktifikation

In November 1999, this construction stage was completed. Production was now operating with five cultivation rooms and an average weekly capacity of 1,800 crates.

1999

Construction of Tunnel Complex Begins

In December 1999, construction of the tunnel complex began. Here, production phases two and three take place.

2000

Further Extension of the Tunnel Complex

In August 2000, the tunnel complex was completed. It consisted of 17 tunnels, and on this basis, production was increased to a capacity of 800 metric tons of colonised substrate per week.

2000

Construction of the Indoor Facility Begins

In September 2000, construction of the indoor facility began. This is where the first production phase takes place.

2001

Start of production of the Indoor Facility

In April 2001, production in the indoor facility started. 2,300 metric tons of fresh substrate per week were now produced by our company.

2001

The Pilzhof Reaches its Output Limit

Pilzhof Wallhausen receives the certificate for the certified quality management system – further expansion from September 2002.

2003

Erweiterung des Tunnelkomplexes

In August 2003, the tunnel complex was extended by six tunnels, to the new total of 23 tunnels. Production capacity was now at 1,000 metric tons of colonised substrate per week.

2003

Erweiterung der Fruktifikation

In September 2003, the fruiting facility was extended by a further four cultivation rooms and a large steam cell. Average weekly capacity was now at 2,520 crates.

2008

Erneute Erweiterung des Tunnelkomplexes

In 2008, the tunnel complex was extended by six tunnels, to a total of now 29 tunnels. Capacity was now at 1,250 metric tons of colonised substrate per week.

2008

Grand Prize of Medium Business 2012

In 2012, for the second time, Pilzhof Pilzsubstrat GmbH was awarded the “Großer Preis des Mittelstandes” (“Grand Prize of Medium Business”) of the Oskar Patzelt Foundation of Leipzig. Michael Schattenberg, the managing director of Pilzhof, is proud of this award: “…but all of this wouldn’t have been possible at all without our dedicated employees.”

Erneute Erweiterung der Fruktifikation

In 2016, the fruiting facility was extended by two further cultivation rooms. This increased the average weekly capacity to 3,500 crates.

2016

2016

Umbau Fruktifikation

In December 2016, one of the two steam cells was converted to a cultivation room, boosting average capacity to 3,512 crates per week.